POWER & INFRASTRUCTURE

Conduit Fill Calculator

Conduit fill percentage and jam-ratio check.

Use this as a design check only. Final conduit sizing must follow adopted code, cable bend-radius limits, pulling tension limits and actual cable mix.

Conduit fill + jam-ratio check

Enter actual raceway ID and cable OD. For NEC compliance, a raceway-type/trade-size table is preferable to nominal diameter.
Fill % = Σ cable cross-sectional area / raceway internal area × 100 NEC Chapter 9 Table 1 general fill limits: 1 cable 53%; 2 cables 31%; 3+ cables 40%. AVIXA CTS-D simple jam ratio reference = conduit ID / average cable OD. IEEE field-bend variant for equal cables = 1.05 × ID / OD; avoid the 2.8–3.2 region.
Conduit ID → areaCable ODs → area used3-cable jam ratio
WORKED EXAMPLE

Example — three similar cables in a bend

Conduit fill alone does not tell the full story. For three similar cables the jam-ratio check helps identify a risk zone where cables may wedge in bends.